edmonton cornerstones project: Suite Success - 11/25/11 02:27 PM
It's been 5 months from start to finish but yesterday our Cornerstone Grant funding came in the mail. We started building the secondary suite in July and final approval came around November 15, 2011, seven days later we got our cheque. Here, here and here are the steps we took through the whole grant process.The biggest delays were permits the longest one took about 6 weeks, our contractor (the guy seriously lost the plot) and finally fireproofing the furnace room ceiling with drywall. 95% of the people we spoke to said it couldn't be done but it was. It took 3 … (0 comments)

 