Prairie Valley Road and Rosedale Avenue Progress Report SCHEDULE IS SUBJECT TO CHANGE
During the weeks of November 22nd to December 6th
Prairie Valley Road
The landscaper will continue placing paving stones in the medians but will now hold off until the spring to complete installation of the turf and plants. The contractor continues to work on the sidewalks as the weather allows. If there are any small portions of sidewalk that they are unable to complete they will be backfilled with crush for the time being. Contractors for Electrical, Telus and Shaw continue to pull and terminate cable underground. This will be ongoing for a while. There is still a small amount of line painting and asphalt patching still outstanding that we are working to complete as well before winter really arrives. |
SCEDT is distributing this message from DOS as a service to our membership. If you have any questions, please contact Devon van der Meulen, District of Summerland. |