It's been 5 months from start to finish but yesterday our Cornerstone Grant funding came in the mail. We started building the secondary suite in July and final approval came around November 15, 2011, seven days later we got our cheque. Here, here and here are the steps we took through the whole grant process.

The biggest delays were permits the longest one took about 6 weeks, our contractor (the guy seriously lost the plot) and finally fireproofing the furnace room ceiling with drywall. 95% of the people we spoke to said it couldn't be done but it was. It took 3 inspections by the city but finally we got it right. The first shot is with gypsum board which is not to code the second two we have drywall and some fireproof duct tape throughout the ceiling.



After our whoops of joy we thought lets do it again. The first attempt was a bit rough going but once you've done the program and been approved it's easier to get your reno team in place and anticipate delays.

 

0 Comments on Suite Success


What does the graphic say?
Leave a response…


(optional)
Spam Prevention:
 
D30_9068r Rainmaker_large

Todd & Danielle Millar

Edmonton, AB

More about me…

Glenn Simon Inc.

Office Phone: (888) 780-5940 x 251

Email Me



Listings

Links

Archives

RSS 2.0 Feed for this blog