Interested in following a residential flip project in real time? Welcome to our "Investor Tag Along"! Your chance to view a flip project in person or via the web.
We are about 75% complete on our Northglenn, Co fix and Flip project. Initial schedule projected a 4 week project, we look to be on time. Holiday breaks are cost us a couple of days, but overall progress and quality is good and we have encountered no major problems to date.
This weekend is interior painting, so we'll have to back off tile install until the air clears. Hardwood floor refinishing is scheduled to start Monday, we'll allow 3 days for patching, sanding and 2 coats of polyurethane. Carpet install to follow.
Status:
- All drywall texture complete
- 6 Panel door installation 100% complete
- Upstairs bathroom tile complete
- Tile selected and on site
- Exterior Trim/eaves paint complete
Underway:
- Interior paint
- Kitchen Tile
- Basement Bath Tile
- Cabinets coming Saturday
- Ordering cabinets and appliances
- Drywall texture in basement bedrooms/living area
This week:
- Refinish Oak hardwood floors
- Complete Tile
- Install Cabinets
- Order Appliances
- Install Basement Bath/Shower Tile
- Install Carpet (basement)