On April 8th the Malibu GreenMachine celebrated the ground breaking of its Highway Enhancement Project with a ribbon cutting ceremony. For those that have not been to Malibu recently the official consrtuction on the highway median began on March 23rd. With a six week construction schedule, the project is to be completed before Memorial Day weekend.
Currently, soil is being removed from the median between Cross Creek Road and Webb Way. The next step is installation of the main lines of the irrigation system, followed by additional topsoil. The last step is the planting of thousands of plants.
Thank you Malibu GreenMachine for all your hard work in making Malibu proud.