Special offer

I-35W River Bridge update

By
Real Estate Agent with Keller Williams Classic Realty 20538434

 

Minnesota Deparment of Transportation - Project Updates
I-35W Bridge over the Mississippi
June 30, 2008
Greetings!  
 

If you have questions, please do not reply directly to this email. Contact

Amy Barrett, Public Information Officer, at (612) 236-6901 or via e-mail at abarrett@flatironcorp.com.

Highway Paving to Begin This Week
 
Aerial view of progress on north side of bridge 
 
Roadway crews will begin paving sections of the I-35W highway north of the river this week. Starting tonight (June 30), crews will begin paving the highway between University Avenue and Second Street Southeast (the area in the foreground of the photo above).  By next week, paving is expected to continue between University Avenue and Fourth Street Southeast.
 

 
Aerial view of main span
  

Meanwhile, the barge crane continues installing pre-cast segments for the northbound and southbound spans of the I-35W Bridge across the Mississippi (see photo above). Of the 120 total segments needed for the main span, 80 already are in place, and approximately 100 will be installed by the end of the week, including all 60 of the segments for the northbound half of the bridge.
 
When the cantilevers extending from both sides of the river are complete, there will be a gap of about 7 feet between them and a difference in elevation of no more than 6 inches. Crews will complete the main span with two "closure pours" of cast-in-place concrete. The closure pour for the northbound side of the bridge is scheduled for the week of July 7, and the southbound side will be closed about 10 days later.

 

Construction Update

 
Concrete segments stored on old highway
 

Other construction activities scheduled for the week of June 30 include:

  • Grading and other roadwork in preparation for paving the highway from Washington Avenue (the road with cars on it in the photo above) to the abutment wall on the south end of the bridge (to the right of the area shown above). Continuing to paint Span 1 on the north side of the river.
  • Continuing to pour the concrete for Span 4, which connects Pier 4 to Abutment 5 on the north side of the river.
  • Installing fencing along the highway from University Avenue to Fourth Street Southeast.

Potential Noise Impacts 

  • As crews pave the roadway on the north side of the project, backup alarms may be increasingly noticeable in that area, especially at night.
  • Following paving, crews will cut expansion joints in the concrete when it is cured. This work involves saws that will create noise intermittently during the day and at night.
  • Toward the end of the week, crews will need to remove sheet pile near the new retaining wall along the exit ramp from northbound I-35W to University Avenue. This work will take approximately two days to complete and will require the use of equipment that causes noise and vibrations. Because this work can be loud, it will only be done during the day, between 7 a.m. and 9 p.m.

Potential Traffic Impacts

As the project progresses, residents and commuters may encounter activities that will affect traffic in the area. In particular: 

  • During roadway paving operations, concrete trucks will travel from the concrete plant on 35W south of Washington Avenue through the project site and up the north bound ramp to Washington Avenue. Trucks will go left on Washington Avenue to 19th Avenue, then across the 10th Avenue bridge to the north side of the project. Most of this activity will take place at night. There will be traffic control at the top of the ramp at Washington Avenue.
  • Crews will periodically close 13th Avenue South from the casting yard entrance to West River Parkway as they transport the last of the pre-cast segments to the river. Hauling operations will take place between 7 a.m. and 7 p.m. intermittently until the end of the week. The road will close for up to 10 minutes each time a segment is moved. 
  • Construction traffic will continue in the vicinity of the site. Some of the streets affected include Second Street Southeast (between 11th Avenue Southeast and Sixth Avenue Southeast), First Street South, Second Street South (between 13th Avenue South and 11th Avenue South), 19th Avenue South and Bluff Street.
  • Due to large crowds attending Sidewalk Superintendent Talks, the bike lane on the west side of the 10th Avenue Bridge will be closed from 11 a.m. until noon on Saturdays until further notice in an effort to ensure the safety of everyone using the bridge. Signs are posted at each end of the bridge noting the restriction. Bikes and pedestrians should use the east side of the bridge between 11 a.m. and noon on Saturdays.

Potential Light Impacts

 

Crews are working night shifts seven days a week on both sides of the river. Lights and construction traffic may be noticeable between 5:30 p.m. and 4 a.m.

 

Planning Your Route to Downtown Minneapolis - If you are planning to drive to downtown Minneapolis, you can use the links below to plan your route:
 
City of Minneapolis Route Planner http://www.ci.minneapolis.mn.us/traffic/routeplannerintro.asp
 
Minnesota Department of Transportation

Help Spread the Word

 

Do you know someone who would appreciate the up-to-date news, first-look pictures and detailed information you get each week? Click on the "Forward e-mail" link at the bottom of this message to pass on a copy of this week's update with an invitation to sign up. 

Getting a Closer Look

Visit the website - The website offers up-to-date information, presentations, graphics, photos and animations, as well as interesting features on workers on the project. You can access the website at www.mndot.gov.
 
Access the webcamsOne provides a panoramic view of the entire construction site, looking east from a rooftop on the north side of the Mississippi River. The other camera is mounted on a light pole on the 10th Avenue Bridge and will provide periodic close-ups of construction activities. To see the webcam views, visit the project website at www.mndot.gov.
 
Attend a Sidewalk Superintendent Talk - These weekly events provide an opportunity to accompany project representatives on a walk across the 10th Avenue Bridge, where you can see the construction workers in action and ask questions about the project. If you'd like to participate, meet in the parking lot in front of the former Grandma's restaurant at 19th and Washington avenues by 11 a.m. on any Saturday.
 
Take a self-guided tour - Signs describing the design/build process are mounted along the 10th Avenue Bridge.
 
Call the hotline - If you have any questions about the project, please call the hotline at (612) 236-6901 between 7 a.m. and 8 p.m. daily. Messages left after 8 p.m. will be returned first thing the morning of the next business day.
 
Request a presentation - Representatives of Mn/DOT and Flatiron-Manson are willing and eager to provide project updates to neighborhood associations, business associations and other groups. To arrange a presentation, please call the hotline, (612) 236-6901.
 
Other than viewing what's happening from the 10th Avenue Bridge, the public is asked to stay away from the bridge construction area for safety reasons. 
 
The Minnesota Department of Transportation (Mn/DOT) and the Flatiron-Manson construction team intend to build a high quality and safe bridge while minimizing disruptions to the surrounding neighborhoods.
 
We will continue to distribute updates weekly and welcome your comments on how to improve the communication process between the project team and the community.
 
For more information on the I-35W project visit www.mndot.gov
or call the I-35W Bridge Hotline at (612) 236-6901.