Interested in following a residential flip project in real time? Welcome to our "Investor Tag Along"! Your chance to view a flip project in person or via the web.
We are about 50% complete on our Northglenn, Co fix and Flip project. Initial schedule projected a 4 week project, we look to be on time. Holiday breaks are costing the schedule a bit, but overall progress and quality is good and we have encountered no major problems to date.
Status:
- Drywall Texture 50% complete (upstairs)
- 6 Panel door installation 50% complete (basement)
- Tile selected and on site
Underway:
- Upstairs bath tile install for tub surround/floors
- Upstairs 6 panel door and closet installs
- Ordering cabinets and appliances
- Drywall texture in basement bedrooms/living area
This week:
- Complete Texture
- Complete Interior door & closet installs
- Order Cabinets & Appliances
- Install Basement Bath/Shower Tile
- Order Carpet (Basement)
- Schedule Interior Paint
Drywall texture "Hopper" used to spray liquid drywall compound on walls for an even "orange peel" texture finish.

Interior 6 Panel doors in basement...Berndt likes to install them "like they grew there" a true finish carpenter...