THE CITY OF PEARLAND -
Cullen Parkway Improvements
Location:
Cullen Parkway between FM518 and BW8
Estimated Completion Date
January 2011
Project Details
Reconstruction of Cullen from FM518 to Beltway 8. Project includes 4-lane divided boulevard with raised median approximately 2.7 miles long. Includes a bridge over Clear Creek and Hickory Slough, the signalization of the intersections at Hughes Rd (CR 403) and Brookside (CR 106) and the shared use trail along the west right-of way. The project will require the acquisition of a small amount of additional ROW for construction of the bridge embankment and detention for the project.
Project Justification
Cullen is on the Major Thoroughfare list which provides another direct route to Beltway 8 as well as into the city itself. This route is currently experiencing congestion as demand for access to the Beltway increases. In addition, PISD plans to construct the new high school along this route which will increase traffic loads as far out as McHard.Additional Information
- Full Construction of McHard Intersection- Storm Drainage built from F.M. 518 to Clear Creek including Detention Pond at Clear Creek
(no storm sewer construction north of Clear Creek)
- Construction of Bridge at Hickory Slough only
- Proposed Widening and Channelization Improvements at Beltway 8 intersection
- 10 ft shared use path and 5 ft sidewalk constructed during adjacent proposed roadway construction